After a new main is installed, which chlorine-related step is described as required prior to flushing?

Study for the North Carolina C-Well Exam 2. Prepare with comprehensive flashcards and multiple choice questions that include hints and explanations. Pass your exam with ease!

Multiple Choice

After a new main is installed, which chlorine-related step is described as required prior to flushing?

Explanation:
Disinfecting the new main with chlorine before flushing is required. After installation, the pipe must be filled with a free chlorine solution at about 25 to 50 mg/L and kept in contact for at least 24 hours. This ensures any bacteria or microorganisms introduced during construction are killed, protecting public health before the line is put into service. After this contact time, the line is flushed to remove the chlorine and any debris, and residual chlorine levels are checked before service begins. Flushing with clean water alone would not disinfect, leaving the line unflushed would risk contamination, and photographing mapping has no role in the disinfection process.

Disinfecting the new main with chlorine before flushing is required. After installation, the pipe must be filled with a free chlorine solution at about 25 to 50 mg/L and kept in contact for at least 24 hours. This ensures any bacteria or microorganisms introduced during construction are killed, protecting public health before the line is put into service. After this contact time, the line is flushed to remove the chlorine and any debris, and residual chlorine levels are checked before service begins. Flushing with clean water alone would not disinfect, leaving the line unflushed would risk contamination, and photographing mapping has no role in the disinfection process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy